M53 closures between junctions 4 and 5 start on 5 December for the Raby Hall bridge. A 50mph limit can run to December 2027, and Raby Hall Road shuts in 2027.

Work to replace the Raby Hall bridge over the M53 starts on Saturday 5 December, with overnight closures of the motorway between junctions 4 and 5. National Highways announced the start on its scheme page on 23 November (M53 Raby Hall Bridge, National Highways).

The bridge carries Raby Hall Road over the motorway near Raby Mere, west of Bromborough. National Highways is replacing its central deck. In spring 2027, Raby Hall Road itself will shut for about nine months while the old deck is demolished and the new one put in.

The December closures

The first job is preparatory work. National Highways lists these closures between junctions 4 and 5:

Date What shuts Hours
Saturday 5 December Northbound carriageway, full closure 9pm to 5am
Sunday 6 December Southbound carriageway, full closure 9pm to 5am
Monday 7 to Wednesday 16 December Lane closures in both directions Round the clock, plus extra overnight lane closures
Wednesday 16 December Northbound carriageway, full closure 9pm to 5am
Thursday 17 December Southbound carriageway, full closure 9pm to 5am

From 5 December, lane one will be closed for about three weeks while the hard shoulder and central reservation are strengthened for the main works, the same page says. National Highways says it will update the programme in the new year.

A 50mph limit that can last until December 2027

The legal order behind the closures is wider than the December dates. National Highways published it in the Liverpool Echo’s public notices on 23 November (M53 junctions 4 to 5 order, Public Notice Portal). It allows:

  • a 50mph limit northbound, from about 2.4km south of the bridge to just over 500 metres north of it
  • a 50mph limit southbound, from just south of junction 4 at Clatterbridge to about 540 metres south of the bridge
  • overnight closures, 9pm to 5am, of both carriageways between junctions 4 and 5, and of the junction 4 and 5 slip roads
  • weekend closures of the same stretch, from Friday 2 April 2027

The order lets the 50mph limit run continuously from 9pm on Monday 30 November 2026 to 5am on Friday 17 December 2027. The notice says the limits and closures apply only when the signs are up. It says diversions will use other M53 junctions and local roads, and will be signed.

The order’s earliest date, 30 November, is five days before the start National Highways gives on its scheme page.

Two weekend closures of the motorway

The main works will need two full weekend closures of the M53 between junctions 4 and 5, one to demolish the old deck and one to put the new one in, National Highways says. Neither weekend has a date yet. The order allows weekend closures from 2 April 2027.

National Highways says it will hold a public information event for people living nearby in the new year. It has not yet given a date or venue.

Part of a £50m programme

Raby Hall is one of several 1970s bridges on the M53 in a programme estimated at £50m (M53 bridges, National Highways). The others are:

  • Upton Road bridge, between junctions 2 and 3, being rebuilt one half at a time until winter 2027
  • Clatterbridge north and south, at junction 4, where dates are still to be confirmed
  • Eastham Viaduct, near junction 5, where joint repairs started in May

What it means for you

  • If you drive the M53 late at night, expect the motorway between Clatterbridge and Eastham to be shut on the nights of 5, 6, 16 and 17 December, with a signed diversion.
  • In the daytime, one lane is closed in each direction for about three weeks from 5 December, so allow longer between junctions 4 and 5.
  • If you use Raby Hall Road, it stays open for now. It is due to shut for about nine months from spring 2027.